Waitetuna residents get road repaired

Waitetuna Valley Road Slip Repairs

Location: Waitetuna Valley Road
Budget: $64,000.00
Due date: 31/07/2010 12:00:00 a.m.
Current stage: Under construction

Project summary

Waitetuna Valley Road is situated approximately half between the townships of Raglan and Whatawhata, extending from SH23 at the northern end and running for 10km to Fillery Road. The project locations are at RP 9.13 and RP 9.27.

Project description

The project involves repairing of two slip sites by constructing two Filtrxx Living Walls.

The contract, valued at $64,000.00, has been awarded to RST and work is expected to be completed by 31 July 2010.