Meridian has announced that construction of the first of 28 wind turbine is underway at the Te Uku wind farm, near Raglan. As reported by the Raglan Website on 28th October construction actually commenced late last month. Although in the following media release Meridian says they can build the towers and turbines in 2 to 3 days, the time from the 28th October to today is six working days.
Meridian Media Release follows:
The Te Uku wind farm is a joint alliance between Meridian Energy and community-trust owned electricity lines company, WEL Networks. At maximum capacity, the wind farm will generate 64.4MWs of electricity, enough to power around 30,000 average New Zealand homes.
The turbines will be constructed with the help of a 600 tonne crane, the largest wheeled crane ever seen in New Zealand.
Te Uku wind farm Project Manager, Robert Batters, says each wind turbine takes around two to three days to construct.
“The process takes place in three main steps. The first component assembled is the base tower section. Then the remaining two tower sections, nacelle and hub are lifted into place.
“Finally, each of the three turbine blades is put in place to complete the process,” explains Mr. Batters.
Mr Batters says the first wind turbine is planned to be generating power before Christmas and all 28 turbines will be generating power by March 2011.
The 600 tonne crane being used to construct the turbines was shipped to New Zealand from Denmark by the KR Wind/NZ Crane Group Alliance especially for the job. It arrived at the wind farm site in mid-October, along with 28 truckloads of associated crane parts. Its boom can be extended to 160 metres, but is configured to 102 metres for the Te Uku turbines.
“Despite its size, the crane only has a width of three metres. This meant we could construct the 26 kilometres of roads on the wind farm site to an absolute minimum width, minimising the environmental footprint on the rural landscape,” says Mr Batters.
The 600 tonne crane is being assisted by a 300 tonne crane and two 100 tonne cranes to complete the turbine erection process.
The Te Uku turbines were manufactured at two sites – the towers in Korea and the actual turbine componentry by Siemens in Denmark.
This is the second Meridian Energy wind farm using Siemens turbine components – the first being the West Wind wind farm at Makara near Wellington.
The turbine towers and components began arriving at the Port of Auckland in September and are progressively being transported to the Te Uku wind farm site. The current plan is for the last of the turbine components to be transported to the wind farm site by mid-December.
Turbine Facts and Figures:
Each turbine, once fully assembled, is 130.5 metres high and weighs 318 tonnes. Each turbine consists of three main parts – the base tower, the nacelle and the blades. Each base tower is 80 metres high and weighs approximately 169 tonnes. The turbine blades are each 49 metres long and weigh 10.9 tonnes. Each nacelle is 3.5 metres in circumference and weighs 81 tonnes. The nacelle is the part of the wind turbine that sits on top of the tower and contains the generator and associated controls. Each of the 28 wind turbines has a maximum generation capacity of 2.3 megawatts. Turbines will generate electricity in wind speeds of between 14km and 90km per hour.