Base Civil, the contractor undertaking the work rebuilding the failed crossings in Bow Street, Raglan has advised retailers and the Raglan Chamber of Commerce on the access routes that will be available while the three stages of the roadworks are underway.  See below for satellite plans below marked up with the detour and access routes.  Click on the images for a more detailed verison. For more information contact Paul Roberts at Base Civil, Phone 847 7233.

Part One: Area around TradeAid Raised crossing in Bow Street

Dates: 19 July 2010 to 25 July 2010

Part Two:  Town Hall side of Bow Street from Bankart St Wainui Road

Dates: 26 July 2010 to 1 August 2010

Part Three: Hrabour View side of Bow Street from Bankart St to Wainui Road

Dates: 2 August 2010 to 8 August 2010


 

Bow Street Works Part One 19 July to 25 July - Image Base Civil

 

 

Bow Street Works Part Two 26 July to 1st August - Image Base Civil

 

 

Bow Street Works Part Three 2 Aug to 8 Aug - Image Base Civil

 